Project Timeline

Follow the timeline to the project completion in July 2015.

Akron Children’s Hospital breaks ground on new parking garage

June 6, 2012
Read more

Akron Children’s announces $200 million expansion

August 12, 2012
Read more

Team

August 13-17, 2012 - A full scale mock-up of Emergency Department helps team design new space
Read more

Parents, kids create wish list for their

August 29, 2012 - Akron Children’s holds town hall meeting so parents can help design new critical care tower
Read more

Designing same-day surgery center

September 10-14, 2012 - A full scale mock-up of outpatient surgery center helps team design new space
Read more

Parents help us build a better hospital

September 25, 2012 - Akron Children’s holds second town hall meeting for families to share their vision
Read more

Putting the you in NICU

October 14-19, 2012 - A full scale mock-up of the neonatal intensive care unit helps team design new space
Read more

Parents weigh in on design of NICU

November 13, 2012 - Akron Children’s holds town hall meeting for parents of “NICU graduates”
Read more

Identifying best practices

December 10-14, 2012 - Teams assemble to discuss and collaborate on creating the most value in design
Read more

Self-described decorators help design facility

January 21, 2013 - Akron Children’s holds parent town hall meeting to get their input
Read more

Final NICU design workshop

February 4-8, 2013 - Akron Children’s NICU team completes final design workshop
Read more

Going, going, gone!

March 2, 2013 - Akron Children’s razes the Wally Waffle building
Read more

2 more buildings razed

March 11, 2013
Read more

Child Guidance building razed

April 30, 2013
Read more

First high–risk delivery paves way for new service

May 10, 2013
Read more

Ceremonial groundbreaking

May 30, 2013
Read more

Two tower cranes added to the construction site

June 27, 2013
Read more

Patients honored by having names spray painted on concrete beams

November 20, 2013
Read more

Christmas tree suspended above construction site during the holidays

December 23, 2013
Read more

Pedestrian bridge put in place between Exchange Street Parking Deck and Kay Jewelers Pavilion

January 4, 2014
Read more

Topping out ceremony held two months ahead of schedule

April 2, 2014
Read more